Keeping a community running smoothly requires the upkeep of Town streets and other road infrastructure. Current and upcoming street construction projects, listed below, show the Town's commitment to a quality network of roads in Riverview.
Street Construction Projects
News
Project | Start Date | End Date |
---|---|---|
Storm & Sanitary Upgrades | May 15, 2024 | July 10, 2024 |
MacAllister Park |
||
Replace Underground Wires | May 15, 2024 | June 30, 2024 |
Henderson Avenue |
||
New Traffic Signal | November 4, 2024 | November 30, 2024 |
Coverdale @ Golf Club Road |
||
Water Main Renewal | May 27, 2024 | July 31, 2024 |
Blythwood Avenue |
||
Street Reconstruction | June 15, 2024 | September 30, 2024 |
Mitton Road (street reconstruction, culvert) - July 2 Manning Road (street reconstruction, watermain, sewers) - July 29 Sherwood Avenue (street reconstruction, watermain, sewers) - July 29 Suffolk - Strathmore to Crystal (street reconstruction, watermain, sewers) - May 6 Westview Terrace (street reconstruction, watermain, sewers) - July 2 |
||
Asphalt Seal | May 27, 2024 | July 31, 2024 |
Birkdale Drive Darwin Drive Elmore Court Innwood Court Ridgeway Drive Windsor Street
|
||
Surface mill, Asphalt Overlay & Curb Replacement | April 29, 2024 | July 31, 2024 |
Hillsborough Road (Old Coach to Harmony) - Starts April 29, 2024 Wilson Road (Estimated to start May 27, 2024) Yale Avenue (Estimated to start May 27, 2024) |
||
Runneymeade - Water Tank Epoxy Recoating | April 14, 2024 | June 18, 2024 |